—Construction schedule · Avianca
00Summary
Estimated duration
≈ 6 weeks
Working hours
Monday to Friday, office hours. Saturdays optional, by prior agreement with the site supervisor.
Commercial terms
Work will commence upon receipt of the 50% advance payment.
Site coordination
Dumpster locations for demolition debris will be coordinated with Avianca.
00Progress
0%Overall
progress
progress
0%
01–05Schedule
Suite
Aug 3Aug 10Aug 17Aug 24Aug 31Sep 7
Office Maintenance
209approx. 2 weeks
Phase 01
Phase 03
210approx. 2.5 weeks
Phase 04
211approx. 2 weeks
Phase 01
Phase 05
Security
203approx. 2 weeks
Phase 03
204approx. 1 week
Phase 02
205approx. 4 weeks
Phase 03
01–05Phases
01
Pending
Demolition & new walls
PeriodAug 10 – 15, 2026
Progress0%
SUITE 209Office Maintenanceapprox. 2 weeks
- Provide, install & modify (3) new accordion doors in the security area
- Remove walls from Security GM & Supervisor office (back of the room)
- Provide new wall (10 LF) for security closet, customized to fit approx. 75" tall
SUITE 211Office Maintenanceapprox. 2 weeks
- Interior partition demolition
- Install new wall, 8 LF (to match existing wall level, not from F.F. to RCP)
- Patch and paint (Print Room & Supervisor office)
02
Pending
Security door — Suite 204
PeriodAug 17 – 22, 2026
Progress0%
SUITE 204Security areaapprox. 1 week
- Install a lockable door in the security area
- Repair walls and paint
03
Pending
Security rooms build-out
PeriodAug 24 – 29, 2026
Progress0%
SUITE 209Office Maintenanceapprox. 2 weeks
- Patch and paint walls (color provided by Avianca)
- Coordinate with Avianca dumpster locations for demo debris
SUITE 203New security roomapprox. 2 weeks
- Frame new opening for new door
- Frame new wall, 6 LF (to match top level of existing wall)
- Provide and install (1) customized folding door for storage
- Data drop install (1)
- Power drop (1)
- Relocate (1) light switch next to new door
- Provide and install (1) 2'×2' light (match existing)
SUITE 205Securityapprox. 4 weeks
- Secure & install (3) new 2'×2' lights
- Provide one CCTV drop (1)
- Provide one data drop (1)
- Provide & install new interior door & frame, 36", between rooms
- Patch and paint walls
- Coordinate with Avianca dumpster locations for demo debris
04
Pending
Flooring & electrical — Suite 210
PeriodAug 31 – Sep 5, 2026
Progress0%
SUITE 210Office Maintenanceapprox. 2.5 weeks
- Replace door (door provided by Avianca)
- Remove flooring, approx. 630 SQFT in 2 layers — laminate & carpet (desk office area and small kitchen)
- Patch and paint walls
- General painting of Office 210
- Furnish & install new laminate flooring & 5-1/4" base — approx. 630 SQFT & 150 LF of base
- Relocate electrical outlets if necessary — outlets for refrigerator, microwave, coffee maker & toaster
- Supply and installation of electrical wiring from the office to the electrical room
- Supply and installation of (4) new circuit breakers to support additional voltage load
- (8) electrical outlets (power points)
- (8) data points (low-voltage / data outlets)
- Coordinate with Avianca dumpster locations for demo debris
05
Pending
Custom door & final paint
PeriodSep 7 – 12, 2026
Progress0%
SUITE 211Office Maintenanceapprox. 2 weeks
- New custom door (height aligned with top of wall)
- General painting of new walls
- Coordinate with Avianca for dumpster locations for demo debris